Montta powerplant bridge renovation
Duration: 2/2024–10/2024
Customer: Fortum Power and Heat Oy / POP-ELY
Location: Muhos
Description: The project involves the renovation of the bridge at Montta hydropower plant. The renovation includes, among other things, renewing the surface structures of the deck and edge beams, replacing railings, repairing concrete damage on the bridge, and updating the lighting. The work will be executed in two phases during the years 2024 and 2025. The project implementation method is a total contract.
Our assignment includes supervision of the bridge repair work and acting as the project safety coordinator during construction.